Abell Point Marina restoration on time, on budget!

Posted by:

This week marks the completion of the on-water restoration project at Abell Point Marina in the wake of the Tropical Cyclone Debbie. In the immediate aftermath, 20% of the on-water berthing at Abell Point was damage amounting to approximately 120 berths in this 507-wet berth marina. In a coordinated effort between Superior Jetties, CGU Insurance and Oceanic Marine Risk, the restoration works commenced 3 April, a mere five days after the cyclone passed over the Whitsundays.

In the initial stages of the project a team of volunteers from BIA (Boating Industry Australia) Queensland, arrived on-site to assist with the make-safe stage of the restoration project. Experienced marine trades personnel from marina managers, to pontoon specialists arrived on-site, including representatives from Superior Jetties to offer support and assist with commencing repair works.

Within days a temporary walkway for L Arm and the marina’s fuel dock was fitted, and by week six the walkway had been replaced for new.

With considerable coordination between the Superior Jetties and marina team, commercial operators and private vessels were relocated to the south marina for the pontoon replacement works to commence. Abell Point Marina is the busiest commercial marina in the region and with the Whitsunday region being so reliant on the tourism sector, a priority for the project was to ensure minimal disruption to the marina’s on-water tourism operations whilst the repair works commenced.

Superior Jetties, Project Manager, Ryan Hogan remarked of the project, “This project has been the culmination of our team down south working some very long hours to produce a fantastic product; and outstanding subcontractors who went above and beyond to get the marina operational again. It’s been a real pleasure to work in North Queensland again and with a client that’s dedicated to running a truly world class marina. This has definitely been the best project team I’ve ever had the pleasure of working with.”

From initial damage assessment, to temporary repairs around the marina, from demolition of debris to piling works and the manufacture/ transportation and installation of the new arms – H/ J/ K/ F/ G and A – the team coordinated by Superior Jetties worked tirelessly to restore the marina to 100% capacity. Mr Hogan goes on to give a special mention to services provided throughout the project by Orca Marine Services, Proserpine Electrical, Whitsunday Drainage Contractors and Pacific Marine Group.

With a busy cruising season scheduled, the launch of a new Abell Point Flight Collection from the marina’s heli-pads and the opening of their floating customer lounge Ocean Club, the timing of the project completion was essential to ensure business as usual. To round off a challenging year and give cause for celebration, Abell Point Marina took out the coveted Marina of the Year Award at the Marine17 conference in August.

Luke McCaul, General Manager, Abell Point Marina explains “To have the pontoons replaced and operational in time for our cruising season was essential for the marina, but also for the region. The Whitsundays has bounced back from this weather event in record time and the natural environment around the islands is following suit.” Mr McCaul goes on to say “The start of the year was a challenging time for the marina team including our valued operators and tenants, but the future is looking bright and the completion of the project on time and on budget is a credit to the hard work and commitment of the team, our contractors and our relationship with our insurers.”

The entire restoration project has been captured by Superior Jetties in short video

0

Making more of marina space

Posted by:

Last week, Nicole Stewart and I were lucky enough to get a tour of the new 240-berth drystack facility at East Coast Marina, Manly Boat Harbour, Brisbane – the largest boat harbour facility in the Southern Hemisphere.

Marina manager, Steve Newbury gave us a tour of the facility which is 80% full and filling up.  The drystack storage accommodates vessels up to 10m, perfectly complementing the 365 wet slips also on offer.

This is an industry-leading approach to boat storage, given the trend towards larger boats and Australia’s push to attract superyachts to our waters. Drystack storage frees up on water space to allow marinas to create the larger berths required to accommodate the migrating southern fleet and visiting superyachts, and enjoy the added revenue they bring.

East Coast Marina is a vibrant boating hub. Its coffee shop, car park and gardens all combine to make it a real gem, whether for boating or visiting for a casual coffee or lunch.

The drystack walls have a unique architectural finish that catches the eye and breaks up the weather without giving the totally boxed in look to the property.

Storage rates include unlimited lift in and lift out, hull wash down and engine flush after each use and complimentary use of maintenance cradles for occasional maintenance. For the client, drystack storage means more security, less maintenance and no hassle of trailer launching and retrieval.

East Coast Marina was the first marina in Queensland to gain full Clean Marina Status in 2006 and with the new drystack storage facility, this continues the marina’s commitment to an innovative, cutting-edge environmental approach.

East Coast Marina’s focus is on reducing our environmental footprint in the most sustainable model possible. They harvest rain-water for boat washing, motor flushing and landscape irrigation. Sewerage pump out and disposal, and grey water recovery and treatment systems are also provided.

There is a video of the site at: http://www.eastcoastmarina.com.au

0

Birkenhead Point Marina floating office becomes the hub

Posted by:

Since its official opening in September, the upgraded Birkenhead Point Marina, on Iron Cove Bay, Sydney has been attracting a new wave of visitors and clients.

The 18 month redevelopment, undertaken by Superior Jetties, improves the facilities and amenities available to tenants and the Sydney boating public.

According to Marina Manager, Philip McGowen, the most significant additions include the new A arm jetty with 14 berths for super yachts up to 40m, a full-service floating fuel dock and a floating kiosk for drinks, snacks, ice, bait and essential boating items.

The marina now has a total of 201 berths as well as onshore kayak storage.

Luke Tapfner, Superior Jetties project manager said that the floating multi-use office and kiosk was part of the original concept and he worked closely with the marina team on the design and planning.

“The brief was to create a floating platform for central office that would provide ease of access and act as a café, office, multi-task area that people could notice, rather than being hidden away.

“We established what size they wanted it, designed the electricity and waste water requirements and then estimated the right weights and building materials to get the correct freeboard to meet up with the marina,” explains Luke.

The finished product comprises four Elite pontoons, chosen for their ease of joining. The structure is located in a central position, adjacent to the fuel dock and, as Phil asserts, it has become something of a social hub.

“We love it! It’s great. It’s very stable, right in the thick of things. Everybody comments on it. It’s a deep maroon colour and very well signed, with tables and chairs out the front and the smell of fresh coffee. It has become a real hub.”

0

Look back at 2013

Posted by:

Welcome everyone to my first blog of 2014.  I hope you all had a break over the holidays and enjoyed some family time.  We are back to work at Superior with some exciting projects this year.  Over the break I had a chance to reflect on some of the highlights of 2013.  Superior completed projects in South Bund Bonded Marina in Shanghai, Portland Harbour Marina, Portland Victoria, Rivergate Marine,  Queensland and Nadi, Fiji to name a few.  It is amazing that the large and small projects together deliver the reputation we enjoy today after 25 years.

The 25 year milestone was celebrated with an event at Sanctuary Cove International Boat Show 2013 with whom we have shared our main marketing activity for the same years since 1988.

We recently had 2 people approach us with interesting feedback.  Mike stopped me in a coffee shop to let me know that the shock absorbers we made 10 years ago are still protecting his boat and lift from excessive wakes on the main river.  The other request was to investigate adding kayak berths to a recently completed mini marina.  This was in a special request from a customer and shows that the trend toward kayaks becoming the entry level to boating is a real event.  We need to consider the needs of these boaters and modify our infrastructure to suit in way that accommodate easier berthing and egress to the craft, better storage and security in our facilities.

In 2014 we are embarking on a redevelopment of the Sydney Birkenhead Marina.  This involves adding new berths while reconfiguring the existing layout and adding fuel facilities.  This is being done using the Superior Elite timber whaler system and promises to be a landmark project for us in the Sydney market.

All the best in 2014